An excavation plan for trenches less than 5 feet deep must include both an excavation or trenching plan and an Activity Hazard Analysis (AHA). This requirement aligns with safety standards meant to mitigate the potential hazards associated with excavation activities, regardless of the depth.

The excavation/trenching plan outlines the specific procedures to ensure safety during the excavation process. This documentation typically includes information about soil conditions, access and egress points for workers, and any necessary protective systems, such as shoring or sloping. Additionally, an AHA assesses potential hazards related to the excavation and establishes protocols to prevent accidents.

Incorporating both elements ensures that all safety measures are systematically addressed, providing a comprehensive approach to managing risks during excavation tasks. This approach not only meets regulatory requirements but also promotes a culture of safety on-site, where potential risks are acknowledged and managed proactively.

The other options do not encompass the necessary components for effective planning and safety in excavations, which is why they fall short of the requirements outlined in safety standards. Without a detailed plan and analysis, the risk of overlooking critical safety measures increases, potentially endangering workers' safety.